Scenario: Zero-Downtime Release

📘 Know

Be able to explain it and pass its lab once. Phase 8 of the Learning Path.

Builds on: Deployments & Rollouts · Services & Ingress · Probes & Observability · Scheduling & Shutdown

Situation​

A checkout API runs 6 replicas behind an Ingress. Every deploy produces a short burst of 502s, and last quarter a release with a bad config took checkout down for 20 minutes because nobody noticed until customers complained. The team wants deploys that users never notice, and a way to expose risky releases to a small share of traffic first.

Requirements​

RequirementFailure it prevents
No errors during a normal rollout502 bursts while Pods start and stop
Capacity never drops below 6 during a releaseLatency spikes when fewer Pods take full traffic
Instant, complete rollback for risky releasesA 20-minute outage while someone works out what changed
Expose risky changes to around 10% of users firstA bad release reaching everyone at once
No new tooling required for the basic pathBlocking the fix on a service-mesh project

Architecture​

Left: blue/green, where Service web selects version=green so all traffic goes to web-green while web-blue stays idle for rollback. Right: canary, where Service web selects app=web so traffic splits by replica count between web-stable with 9 replicas and web-canary with 1Left: blue/green, where Service web selects version=green so all traffic goes to web-green while web-blue stays idle for rollback. Right: canary, where Service web selects app=web so traffic splits by replica count between web-stable with 9 replicas and web-canary with 1

Figure S3-1: Blue/green and canary with core primitives. Amber is the Service selector, the one field you change. Green is the new version, grey the idle old version, blue the stable version still serving.

Kubernetes resources used​

ResourceRole hereReference
Deployment rolling updateThe default path for every releaseDeployments & Rollouts
Readiness probe + preStopNo traffic to Pods that aren't ready or are shutting downProbes & Observability · Termination sequence
Service label selectorThe switch for blue/green; the pool for canaryServices & Ingress
PodDisruptionBudgetKeeps capacity during node maintenance, not just deploysScheduling & Shutdown
Two DeploymentsBlue/green and canary both need both versions running at onceDeployments & Rollouts

Walkthrough​

1. Fix the rolling update first​

The 502s come from shutdown, not startup (→ Figure 16-1). When a Pod is deleted, the kubelet sends SIGTERM while kube-proxy and the Ingress controller are still removing the Pod from their endpoints. For a second or two, requests still arrive at a process that has stopped accepting them.

SettingValueWhat it fixes
maxUnavailable0Capacity never drops below 6
maxSurge1 (or 25%)Speed vs extra cost during the rollout
readinessProbeReal /ready endpointNew Pods get traffic only when they can serve
preStop sleep10 sPod keeps serving while endpoints update everywhere
App SIGTERM handlingFinish in-flight requests, then exitNo connections dropped mid-request
terminationGracePeriodSeconds45Longer than preStop + drain, so nothing is SIGKILLed
minReadySeconds10A Pod that crashes right after becoming Ready doesn't count

With these, the rolling update is the everyday path. The rest of this page is for releases risky enough to need more.

2. Blue/green for instant, complete rollback​

Run both versions at full size. The Service selects one by a version label. Cutting over is one patch; rolling back is the same patch in reverse, with no Pods starting.

apiVersion: apps/v1
kind: Deployment
metadata:
name: web-green
spec:
replicas: 6
selector:
matchLabels: {app: web, version: green}
template:
metadata:
labels: {app: web, version: green}
spec:
containers:
- name: web
image: nginx:1.28
ports: [{name: http, containerPort: 80}]
readinessProbe:
httpGet: {path: /, port: http}
---
apiVersion: v1
kind: Service
metadata:
name: web
spec:
selector: {app: web, version: blue} # still on blue
ports:
- {port: 80, targetPort: http}
kubectl rollout status deployment/web-green # all 6 Ready first
kubectl patch service web -p '{"spec":{"selector":{"app":"web","version":"green"}}}'
# rollback: the same patch with "blue"
kubectl scale deployment web-blue --replicas=0 # only after green has proven itself

3. Canary for gradual exposure​

Both Deployments carry app: web, and the Service selects only app: web. Traffic splits roughly by replica count: 9 stable + 1 canary ≈ 10% to the canary.

apiVersion: apps/v1
kind: Deployment
metadata:
name: web-canary
spec:
replicas: 1
selector:
matchLabels: {app: web, track: canary}
template:
metadata:
labels: {app: web, track: canary} # app=web puts it behind the shared Service
spec:
containers:
- name: web
image: nginx:1.28
ports: [{name: http, containerPort: 80}]
readinessProbe:
httpGet: {path: /, port: http}

Promote by updating the stable Deployment's image and scaling the canary to 0. Abort by scaling the canary to 0.

Canary methodPrecisionNeeds
Replica ratio (this page)Coarse: 1 of 10 = 10%, 1 of 3 = 33%Nothing extra
Ingress controller canary annotationsPercent or header-basedController support
Gateway API HTTPRoute weightsExact percentages, standard APIA Gateway controller
Service mesh / Argo RolloutsWeights plus automated metric analysisExtra platform components

4. Decide per release​

ReleaseStrategyWhy
Routine code changeRolling updateCheap, safe with the fixes in step 1
Big bang change, versions can't coexistBlue/greenInstant, complete switch and rollback
Risky change, versions can coexistCanaryLimits blast radius while you watch metrics
Database schema changeExpand/contract across releases→ Deployments & Rollouts Q4

How I'd explain this in an interview​

"First I'd separate the two problems. The 502s on every deploy are a shutdown race: SIGTERM arrives while endpoints are still being removed. So the fix is a preStop sleep, proper SIGTERM handling in the app, and a grace period longer than both. Add maxUnavailable zero and a real readiness probe, and ordinary rolling updates become invisible. That covers most releases for free. For risky ones I'd use core primitives before adding tools. Blue/green is two Deployments and a Service selector switch: instant cut-over, instant rollback, at the cost of double capacity. Canary is two Deployments behind one selector, so traffic splits by replica count. It's cheap but coarse, and if we need exact percentages or automatic analysis, that's when Gateway API weights or Argo Rollouts earn their place. The last incident was really a detection problem, so whichever strategy we use, promotion has to be gated on error-rate and latency metrics, not on someone watching."

Follow-up questions​

★★ Canary traffic by replica count is uneven for long-lived connections. Why?

Model answer
  • Clarify: HTTP/1.1 keep-alive, HTTP/2 or gRPC clients?
  • Observe: kube-proxy balances connections, not requests. A client that holds one connection sends all its requests to one Pod.
  • Hypothesise: a few heavy clients pinned to stable Pods make the canary's real share differ from 10%.
  • Fix: balance at L7: an Ingress, Gateway or mesh that spreads requests across Pods, or client-side load balancing for gRPC.
  • Prevent: measure the canary's actual share of requests, not its replica share.

★★ The canary has a higher error rate. How do you roll back, and what did users see?

Model answer
  • Clarify: how long was it live, and what share of traffic did it get?
  • Observe: only requests routed to the canary failed, roughly 10% of traffic for that window.
  • Hypothesise: blast radius = traffic share × time live. That's the point of a canary.
  • Fix: kubectl scale deployment web-canary --replicas=0. The stable Deployment was never touched, so nothing else changes.
  • Prevent: automate the abort: an analysis step (Argo Rollouts, Flagger) that compares canary and stable metrics and scales the canary down without a human.

★★★ Blue/green doubles cost. How would you reduce it?

Model answer
  • Clarify: how long must the old version stay ready for rollback?
  • Observe: the cost is the idle color, and only during the release window.
  • Hypothesise: you pay for instant rollback. Shorten the window or shrink the idle side.
  • Fix: scale green up only for the release, keep blue for a fixed bake time (say 30 minutes), then scale it to 0. Or keep blue at reduced size and let the HPA scale it back up if you switch back, trading rollback speed for cost.
  • Prevent: reserve blue/green for releases that need it; canary or rolling costs almost nothing extra.